LHC Dry-runs and Machine Check-out
DOI:
https://doi.org/10.5170/CERN-2015-002.85Keywords:
LHC, performance, Chamonix.Abstract
During LS1 most of the equipment groups took the opportunity to upgrade, improve and refactor their hardware and software. A particular care is necessary for the operation team during the testing phase before beam commissioning. Some equipment and software tests from the control room have already started early in the year, including the communication with the experiments, RF frequency ramp, LBDS arming sequence etc… The results will be presented. In parallel, regular meetings between OP and the equipment’s group have started for the establishment of a working plan for the final machine check-out. The strategy for the machine preparation from now to the beam commissioning will explained.Downloads
Published
2016-02-02
Issue
Section
Article
License
Authors who publish with this publication agree to the following terms:
- CERN retains copyright and publishes the work licensed under the Creative Commons Attribution License 4.0 that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this series.
- Authors are able to enter into separate, additional contractual arrangements for distribution of the published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this series.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).