Strategy for the first two Months of LHC Beam Commissioning (Commissioning to First Stable Beams)
DOI:
https://doi.org/10.5170/CERN-2015-002.125Keywords:
LHC, performance, Chamonix.Abstract
The 2015 LHC schedule tentatively allocates two months between the start of beam commissioning and the establishment of the first stable beams with a few nominal bunches at top energy. This phase will address the commissioning with beam of all key accelerator systems, taking into account the changes occurred in Long Shutodown 1 (LS1) and new commissioning requirements for the 2015 operational goals. In presence of uncertainties on the key machine and beam parameters, a set of critical measurements to be performed early on in the commissioning are identified in order to establish a validation plan for the machine configuration for the intensity ramp up. In this paper, the strategy for the initial commissioning until the first stable beams is reviewed.Downloads
Published
2016-02-02
Issue
Section
Article
License
Authors who publish with this publication agree to the following terms:
- CERN retains copyright and publishes the work licensed under the Creative Commons Attribution License 4.0 that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this series.
- Authors are able to enter into separate, additional contractual arrangements for distribution of the published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this series.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).