Machine Protection Strategy for LHC Commissioning and Outlook for Future Challenges
DOI:
https://doi.org/10.5170/CERN-2015-002.134Keywords:
LHC, performance, Chamonix.Abstract
During Run 2, when operating at 6.5 TeV and 25 ns bunch spacing, the LHC will accelerate and store beams with an energy of up to 372MJ. A very tiny fraction of this beam can cause severe damage to accelerator equipment if the energy is released in an uncontrolled way. The note addresses the machine protection considerations for the initial commissioning with and without beam and discusses the required (re-)qualifications for subsequent changes of beam/optics parameters during the run. The definition of the new setup beam intensity - impacting commissioning and later operation and machine developments - is recalled. The note will conclude with an outlook on future challenges with respect to machine protection in view of the injector upgrade and HL-LHC.Downloads
Published
2016-02-02
Issue
Section
Article
License
Authors who publish with this publication agree to the following terms:
- CERN retains copyright and publishes the work licensed under the Creative Commons Attribution License 4.0 that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this series.
- Authors are able to enter into separate, additional contractual arrangements for distribution of the published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this series.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (SeeĀ The Effect of Open Access).