Machine Protection Strategy for LHC Commissioning and Outlook for Future Challenges

Authors

  • B. Salvachua CERN, Geneva

DOI:

https://doi.org/10.5170/CERN-2015-002.134

Keywords:

LHC, performance, Chamonix.

Abstract

During Run 2, when operating at 6.5 TeV and 25 ns bunch spacing, the LHC will accelerate and store beams with an energy of up to 372MJ. A very tiny fraction of this beam can cause severe damage to accelerator equipment if the energy is released in an uncontrolled way. The note addresses the machine protection considerations for the initial commissioning with and without beam and discusses the required (re-)qualifications for subsequent changes of beam/optics parameters during the run. The definition of the new setup beam intensity - impacting commissioning and later operation and machine developments - is recalled. The note will conclude with an outlook on future challenges with respect to machine protection in view of the injector upgrade and HL-LHC.

Downloads

Published

2016-02-02